Modified Pi 3 case to fit on top of existing Ethernet Switch
 
Modified Pi 3 case to fit on top of existing Ethernet Switch
  
I started work on the Custom Pi 3 Case.
+
I finished the CAD for the Pi 3 Case. It is ready for 3D Printing.
 +
Here it is:
 +
[[File:Custom Pi3 Case.jpg]]
  
Here is the Bottom Plate:
+
On top of the Pi 3 Case being completed, two Flanges and the remaining timing pulleys were completed.
[[File:Custom Pi bottom.jpg]]
+
 
 +
Bumpers were redone to accommodate the welds on the side of the chassis, drawings were printed, and work on the tangible bumpers is now underway! - Madi
  
 
==Mechanical==
 
==Mechanical==

Latest revision as of 17:32, 19 February 2017

<< PREVIOUS -- NEXT>>
PHOTOS

CAD & Design

CAM Lead- Patrick

Started printing the first of four Flanges meant to go onto the climbing system. Each Flange takes 2:30 hrs to print. Meanwhile other parts that need printing are:

6 17-tooth timing pulleys

Talon covers

Housing Cases for all on-board cameras (cameras for this year are undecided)

Modified Pi 3 case to fit on top of existing Ethernet Switch

I finished the CAD for the Pi 3 Case. It is ready for 3D Printing. Here it is: Custom Pi3 Case.jpg

On top of the Pi 3 Case being completed, two Flanges and the remaining timing pulleys were completed.

Bumpers were redone to accommodate the welds on the side of the chassis, drawings were printed, and work on the tangible bumpers is now underway! - Madi

Mechanical