Build season is the heart of the FRC year. It is the 45 days during which the team's students and mentors put their hearts, minds and hands into designing and building a great robot. Paradoxically, the time seems both far too short and much too long.

This page contains a day by day breakdown of what we did. Dates hyper-links go to the corresponding photo gallery.

Kickoff

  • On Saturday, January 8th, team 1640 students, parents and mentors drove to Upper Darby High School on to watch the events from Dean Kamen’s home in New Hampshire, see the objectives of the 2011 game revealed, examine a mock-up of this year’s play pieces up close, and pick up our kit of parts.
  • We attended seminars immediately following the Logomotion Kickoff.
  • The Team returned to DRC following Kickoff for a read-through of Logomotion's rules.

Week One (1/9-1/15)

Sunday 9-January - Brainstorming

  • Siri Maley & Heather McKown inventoried the Kit-of-Parts (nothing missing) - KOP parts laid out for brainstorm "touch & feel".
  • Siri Maley, Heather McKown & Clem McKown set up a 1/7th-scale mock-up field inclufing scale robots, bonus towers & game pieces
  • Strategy Brainstorm - well attended by 18 students and 14 mentors - we:
  • developed a large number of game-play ideas;
  • focus on what, not how;
  • consolidated, synthesized and built on ideas as teams;
  • presented team ideas;
  • simulated the game on the game table (mock-up field) - multiple itterations; and
  • consolidated , synthesized & built on ideas as a complete team

Monday 10-January (no photos to speak of)

  • FIRSTchoice parts ordered (FTC Kit, Solenoid Kit & Pressure Relief Valve)
  • Made key strategic decisions for DEWBOT VII

Tuesday 11-January - Meeting cancelled due to snow storm

Wednesday 12-January

  • Assembled Functions list - started to assign specifications
  • Arm analysis - started on arm design concepts
  • Started building the first scoring Tower
  • Started cutting Al for Pivots Sides
  • Welcome to new mentor, Juan Posada

Thursday 13-January

  • First Pivot sideplate has been machined - a thing of beauty!
  • Finished cutting Al stock for Pivot sides & tops
  • Continued practice field construction
  • Started prototyping and testing the claw
  • Started work on the Minibot
  • Defined teams and lead mentors for these teams
  • We have Internet!
  • Web-based colaboration file sharing initiated for CAD team
  • Functions and Specifications largely complete

Saturday 15-January

  • Continued claw prototyping
  • Cut stock for Pivot Tubes & Transfer axles
  • Continued to build field pieces
  • Started to play with Tetrix parts for Minibot
  • Specified belts & pulleys for drive-train
  • Started putting 4-linkage arm into Inventor
  • Organized shop & storage
DEWBOT VII Week One Build Season Photo Gallery

Week Two (1/16-1/21)

Sunday 16-January

  • We worked through & articulated our sensor strategy & requirements
  • Which required clearly articulating our autonomous strategy
  • Also provisionally worked through our motor needs
  • Final Pivot Drive stock cut
  • Cut a plane work area on the mill bed
  • 4-bar arm entered into CAD (Molley)
  • Pivot drive pulleys & belts ordered
  • More arm prototype testing
  • Have a reasonable Minibot concept to develop

Monday 17-January

  • Siri's analysis of the 2-joint arm points out the need to manipulate the attitude of the Logo Piece - a strong argument for the 4-bar linkage arm
  • Prototyped the 4-bar linkage arm. It seems we should be able to score on the high targets. On the lower targets, however, we will need to approach the target grid at an angle to stay in the safe zone.
  • During prototyping, conceptualized a lighter variation on the 4-bar arm. Will test Wednesday.
  • Developed the 4-bar linkage arm in CAD
  • Chassis frame is developing in CAD
  • Minibot launch design started

Wednesday 19-January

  • Started improved jaw prototype
  • Started machining Pivot spacers on lathe
  • Building bonus tower
  • Establish material needs for bumpers

Thursday 20-January

  • Finished first bonus tower
  • Completed Pivot spacers
  • Started broaching keyways into miter gears and 9T sprockets

Saturday 22-January

  • Finished broaching keyways into the miter gears
  • Put together our first Minibot (certainly not our last) - did not take it for a vertical walk
  • Atarted cutting custom polycarbonate wheels on lathe
  • Chassis frame has been (somewhat) completed in CAD
  • CAD collaboration software is working - Andrew has Inventor 2011 running and is therefore in the running
  • Made significant progress on arm/claw
DEWBOT VII Week Two Build Season Photo Gallery

Week Three (1/23-1/29)

Sunday 23-January

  • Finished polycarbonate wheels with concave profile for the Minibot
  • 1st Minibot test
  • Chassis designed
  • Cut chassis frame pieces (not done)
  • Bored steering drive pulleys using lathe (done)
  • Bored steering driven pulleys using lathe (incomplete)
  • Tested improved claw with pneumatics

Monday 24-January

  • Finally finished boring drive-train pulleys
  • Pivot Module top & bottom plates complete
  • Drive-train Model has been adapted to the Minibot pole race. Some sample results are available. Light minibots rule, but there are additional (and more nuanced) lessons.
  • Help! My magnetic minibot has fallen off the pole and can't get up! What do I do? Find out here & (esp. for the geeks among us) do the math
  • Minibot gets up the pole now
  • We used the mill to cut lightening holes into the chassis longituninals - both accurate & efficient (not to mention cool)
  • FRP pultursion arrived. We plan to use for the arm.
  • We are, officially, in the groove!

Tuesday 25-January

  • The minibot climbs the pole with battery on-board in 4.5+ seconds - but not every time
  • Almost all chassis frame pieces are cut; weight reduction holes drilled & chamfered
  • Weight reduction holes are drilled in the wheel sprockets (all 8 at a time in the mill)
  • Wood cut for 2nd bonus tower

Wednesday 26-January

  • Snow Storm - No Robotics tonight!
  • But designing continues

Thursday 27-January - No meeting - DRC parking lot not yet plowed

Friday 28-January

  • Assembled test Pivot tube/top using thermal interference. Need to reduce interference to 0.0025". Tortured this test assembly (successful!)
  • Assembled first Pivot tube/top assembly
  • Milled circular keyways in driven steering pulleys (3/16" round in 1" ID)
  • Broached keyways in 56T driven pulleys
  • Cut more frame pieces
  • Started work on frame assembly jig

Saturday 29-January

  • Assembled all Pivot tubes/tops (thermal interference)
  • Lubricated all BainBot P60 gearboxes, assembled with RS-540 motors onto the Pivot Module bottom plates
  • Assembled all Coaxial drive shafts/miter gears
  • Assembled all transfer axles
  • Pressed first 1" bearing into a Pivot Module bottom plate
  • Milled frame front/back welding template and cut alignment holes in frame pieces
  • Made a faster minibot - still under development
  • Arm design complete - ready to start fabrication
  • Have video feed working
DEWBOT VII Week Three Build Season Photo Gallery

Week Four (1/30-2/5)

Sunday 30-January

Monday 31-January

Tuesday 1-February

Wednesday 2-February

Friday 4-February

Saturday 5-February