Difference between revisions of "FTC 7314 Engineering Notebook 2015-10-19"
From DEW Robotics
MaiKangWei (talk | contribs) (→Action and idea Journal) |
MaiKangWei (talk | contribs) |
||
Line 17: | Line 17: | ||
!Objectives / Systems !! Hypotheses, tests, observations, conclusions, plans | !Objectives / Systems !! Hypotheses, tests, observations, conclusions, plans | ||
|- | |- | ||
− | | ''' | + | | '''Daniel,Myles, Trever and braden worked on building the Intake''' |
| | | | ||
− | * | + | * Daniel worked on the intake . he was Myles's sensei. |
+ | * Myles finished the tank treads and helped Daniel in the Intake. | ||
+ | * Seth helped Clem and wade finish one of the main tank treads. | ||
+ | *the team decided on a new concept for the robot, it seems similar. we all got to work with the new desine. and got a lot done. | ||
+ | * Trevor and Braden manufactured a servo intake beater bar, then showed others how to build it. | ||
|- | |- | ||
| '''Objective in bold''' | | '''Objective in bold''' | ||
| | | | ||
− | * | + | * |
|} <!-- End of tasks table; DO NOT REMOVE --> | |} <!-- End of tasks table; DO NOT REMOVE --> |
Revision as of 00:32, 20 October 2015
Competition Season Meeting
Meeting Date | Meeting Time | Location | Attendees |
---|---|---|---|
19-October-2015 | 6:00-9:00 PM | TCHS Brandywine |
Objectives / Systems | Hypotheses, tests, observations, conclusions, plans |
---|---|
Daniel,Myles, Trever and braden worked on building the Intake |
|
Objective in bold |
|
Action and idea Journal
Tasks | Reflections |
---|---|
Task in bold |
|
Task in bold |
|
Recorded by: | Date: | Journal Editor: | Date: |
---|---|---|---|