(30-November)
(30-November)
Line 26: Line 26:
 
# Drill the output shaft bushing holes on the worm gearbox to 3/8" (from 8mm)
 
# Drill the output shaft bushing holes on the worm gearbox to 3/8" (from 8mm)
 
# Replace output shaft bushings with 0.25" ID bronze flange bushings (1/2" long)
 
# Replace output shaft bushings with 0.25" ID bronze flange bushings (1/2" long)
 +
# Cut (3) 3/32" keys: for worm gear and (2) for Hubs
 
# Assemble output worm gear and shaft w/ key
 
# Assemble output worm gear and shaft w/ key
 
# Re-assemble input shaft with dual motors and worm
 
# Re-assemble input shaft with dual motors and worm
# Bore  
+
# Bore (2) driven Hubs to 0.250" ID and broach 3/32" keyways
 +
# Reassemble arm drive shaft (including tubing portion)
  
 
----
 
----
 
[[Category:FTC]][[Category:Block Party!]]
 
[[Category:FTC]][[Category:Block Party!]]

Revision as of 01:33, 1 December 2013

2-November

Ramp Riot!

7-November

9-November

11-November

14-November

15-November

16-November

21-November

30-November

Nicholas & Julie Christopher work on communications issues
Programming: Nicholas & Julie worked on communications issues with the Samantha. These were not resolved during the meeting.

Mechanical: Rebuilt the arm drive by replacing the original 4.7mm D-shaft with a 0.25" diam steel shaft with 3/32" keyway. His change required the following:

  1. Bore out the driven brass worm gear to 0.250" ID
  2. Broach a 3/32" keyway in the worm rear ID
  3. Drill the output shaft bushing holes on the worm gearbox to 3/8" (from 8mm)
  4. Replace output shaft bushings with 0.25" ID bronze flange bushings (1/2" long)
  5. Cut (3) 3/32" keys: for worm gear and (2) for Hubs
  6. Assemble output worm gear and shaft w/ key
  7. Re-assemble input shaft with dual motors and worm
  8. Bore (2) driven Hubs to 0.250" ID and broach 3/32" keyways
  9. Reassemble arm drive shaft (including tubing portion)